Pandora Street

First Things First

We held a kick-off meeting on December 17th with all the trades involved in building the new Crag X. After introductions, Stewart Story of Story Construction (our General Contractor) went over timelines, organization and execution of our plan.  Meeting adjourned and then off to plan the first day of work - bringing down the existing building.

Working on our project is a fine team of professionals. In no real order they are:

The kick-off meeting.

The kick-off meeting.

  • Story Construction - General Contractor
  • Chandler Associates Architecture - Architect
  • Londong Mah Asociates - Structural Engineering
  • Avalon Mechanical - Mechanical Engineering
  • Magma Electrical - Electrical Engineering
  • Ryzuk Geotech - Geotechnical Engineering
  • Focus Engineering - Civil Engineering
  • Michell Excavating - Civil Contractor
  • Nanaimo Precast - Precast 
  • Alliance Engineering Works - Structural Steel Contractor
  • Oceanview Mechanical - HVAC/Mechanical Contractor
  • Brewis Electric - Electrical Contractor
  •  Pino-Lite Glass - Glazing
  • Parker Johnson Roofing - Roofing Contractor
  • Gordon N Gordon - Interior Contractor

 

We've Begun!

After a long time and a lot of work we are finally able to announce the start of our move to Pandora Street!

At 11am on December 12, 2014 we signed the construction contract for our new building. Work at the site should begin this week and we expect to be open for climbing early summer 2015.

CXPandoraFront

We will be updating you on our progress as we go on this blog, so check back for posts, photos and more.

The climbing community in Victoria is great, and we can't wait to have you all climbing in our new gym. Drew can't wait either!

Thanks for all of your support over the last twenty years,

Nikolai and Kenneth